Air Springs (Air Suspension Bellows)

—

Prepared on: 29 October 2026 · Prepared with Building Business DPR (buildingbusiness.in)

01 Project at a glance

Total project cost
₹17.85 L
Term loan from bank
₹11.60 L
Promoter’s contribution
₹1.79 L
Subsidy
₹4.46 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-6.15 L
Average DSCR
-1.44
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Build rubber air-spring bellows on an automatic building system for vehicle suspensions and industrial actuators.

Main product or serviceAir Springs (Air Suspension Bellows)
Installed capacity per year (at 100%)10,000 units

04 Market

  • Commercial vehicle fleets and body builders
  • Trailer makers
  • Packaging, conveyor and lift machine makers
  • Laundry, weighing and textile machine makers
  • Direct supply to OEMs
  • Auto spare-parts dealers for replacement

05 Plant and machinery

ItemQty₹Total ₹
Fully automatic uni-stage air-spring building system116,50,00016,50,000
Other equipment150,00050,000
Total17,00,000

Pre-filled from: PMEGP sample project report — Air Spring Manufacturing Unit (prepared by Udyami/Samadhan). Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Bellows (rubber carcass material) — main component
  • Bead plates, girdle, bumper and piston — metal and rubber parts
  • Air fittings, nuts, bolts and mounts — assembly hardware

07 Cost of project

₹ in lakh
Plant and machinery17.00
Contingency0.85
Total fixed capital17.85
Working capital margin0.00
Total project cost17.85

08 Means of finance

₹ in lakh%
Promoter’s contribution1.7910.0
Subsidy4.4625.0
Term loan from bank11.6065.0
Total17.85100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance0.360.360.360.360.360.360.36
Insurance0.090.090.090.090.090.090.09
Total cost of operations3.333.333.333.333.333.333.33
Operating profit (EBITDA)-3.33-3.33-3.33-3.33-3.33-3.33-3.33
Depreciation2.682.281.931.641.401.191.01
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan1.261.090.890.700.500.300.11
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-7.26-6.69-6.15-5.67-5.22-4.82-4.44
Income tax0.000.000.000.000.000.000.00
Profit after tax-7.26-6.69-6.15-5.67-5.22-4.82-4.44

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-7.26-6.69-6.15-5.67-5.22-4.82-4.44
Depreciation2.682.281.931.641.401.191.01
Cash accruals (PAT + depreciation)-4.58-4.41-4.22-4.02-3.83-3.63-3.43
Term loan repaid0.891.791.791.791.791.791.79
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-5.47-6.20-6.00-5.81-5.61-5.41-5.22
Cash and bank-5.47-11.67-17.68-23.48-29.09-34.51-39.73

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)6.256.256.256.256.256.256.25
Reserves and surplus-7.26-13.95-20.10-25.77-30.99-35.81-40.25
Term loan outstanding10.718.937.145.363.571.790.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities9.701.22-6.71-14.17-21.17-27.78-34.00
Net fixed assets15.1712.9010.969.327.926.735.72
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-5.47-11.67-17.68-23.48-29.09-34.51-39.73
Total assets9.701.22-6.71-14.17-21.17-27.78-34.00

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-1.55-1.16-1.24-1.34-1.46-1.59-1.76
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-1.44
Lowest DSCR-1.76
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation2.682.281.931.641.401.191.01

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
111.601.260.8910.71
210.711.091.798.93
38.930.891.797.14
47.140.701.795.36
55.360.501.793.57
63.570.301.791.79
71.790.111.790.00

17 Licences and registrations

  • Udyam
  • GST
  • Trade licence
  • Pollution Control Board consent (rubber processing)
  • Factory licence
  • Customer or AIS/BIS approvals where buyers require them for vehicle parts

18 Government schemes that may apply

  • Prime Minister's Employment Generation Programme (PMEGP)
  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)

19 Sources

  1. PMEGP sample project report — Air Spring Manufacturing Unit (prepared by Udyami/Samadhan) — https://pmegp.msme.gov.in/Home/DownloadDocument?fileName=Documents/ProjectSampleReport/Air_Springs_%28_Samadhan_Projects_%29.pdf

This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.