01 Project at a glance

Total project cost
₹3.15 L
Term loan from bank
₹2.05 L
Promoter’s contribution
₹0.32 L
Subsidy
₹0.79 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-3.46 L
Average DSCR
-7.27
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Assemble and test alternators that charge vehicle batteries and power lights, wipers and fans.

Main product or serviceAutomobile Alternators
Installed capacity per year (at 100%)10,000 units

04 Market

  • Auto spare-parts dealers
  • Vehicle repair workshops
  • Fleet owners
  • Spare-parts wholesalers and retailers
  • Direct supply to workshops

05 Plant and machinery

ItemQty₹Total ₹
Pneumatic machine and pneumatic tools100
Drilling, tapping and grinding machines100
Air compressor, soldering set-up, bench vice and 2 hand presses100
HV breakdown tester, 1,000 V meggar, multimeter and ammeter100
Vernier callipers, micrometer, temperature-rise tester and tachometer100
Hot performance, high-speed, endurance and performance test rigs100
Dies, moulds, jigs, fixtures and tooling100
All equipment incl. office furniture and pre-operative expenses (total)13,00,0003,00,000
Total3,00,000

Pre-filled from: KVIC Project Profile — Alternators for Automobiles (PMEGP). Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Alternator parts and sub-assemblies — ₹78,00,000 a year in the profile
  • Labels and packing material — ₹85,000 a year in the profile

07 Cost of project

₹ in lakh
Plant and machinery3.00
Contingency0.15
Total fixed capital3.15
Working capital margin0.00
Total project cost3.15

08 Means of finance

₹ in lakh%
Promoter’s contribution0.3210.0
Subsidy0.7925.0
Term loan from bank2.0565.0
Total3.15100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance0.060.060.060.060.060.060.06
Insurance0.020.020.020.020.020.020.02
Total cost of operations2.962.962.962.962.962.962.96
Operating profit (EBITDA)-2.96-2.96-2.96-2.96-2.96-2.96-2.96
Depreciation0.470.400.340.290.250.210.18
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan0.220.190.160.120.090.050.02
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-3.65-3.55-3.46-3.37-3.29-3.22-3.16
Income tax0.000.000.000.000.000.000.00
Profit after tax-3.65-3.55-3.46-3.37-3.29-3.22-3.16

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-3.65-3.55-3.46-3.37-3.29-3.22-3.16
Depreciation0.470.400.340.290.250.210.18
Cash accruals (PAT + depreciation)-3.18-3.15-3.12-3.08-3.05-3.01-2.98
Term loan repaid0.160.320.320.320.320.320.32
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-3.34-3.47-3.43-3.40-3.36-3.33-3.29
Cash and bank-3.34-6.80-10.23-13.63-16.99-20.32-23.61

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)1.101.101.101.101.101.101.10
Reserves and surplus-3.65-7.21-10.66-14.03-17.33-20.55-23.71
Term loan outstanding1.891.581.260.950.630.320.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities-0.66-4.53-8.30-11.99-15.60-19.13-22.60
Net fixed assets2.682.281.931.641.401.191.01
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-3.34-6.80-10.23-13.63-16.99-20.32-23.61
Total assets-0.66-4.53-8.30-11.99-15.60-19.13-22.60

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-7.80-5.84-6.26-6.76-7.34-8.03-8.86
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-7.27
Lowest DSCR-8.86
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation0.470.400.340.290.250.210.18

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
12.050.220.161.89
21.890.190.321.58
31.580.160.321.26
41.260.120.320.95
50.950.090.320.63
60.630.050.320.32
70.320.020.320.00

17 Licences and registrations

  • Udyam
  • GST
  • Trade licence
  • Pollution consent as per state category
  • Trademark for your brand (optional)

18 Government schemes that may apply

  • Prime Minister's Employment Generation Programme (PMEGP)
  • Pradhan Mantri MUDRA Yojana (PMMY) – Shishu, Kishor, Tarun, Tarun Plus
  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)

19 Sources

  1. KVIC Project Profile — Alternators for Automobiles (PMEGP) — https://pmegp.msme.gov.in/Home/DownloadDocument?fileName=Documents/ProjectSampleReport/ALTERNATORS_FOR_AUTOMOBILES_%28_RURAL_ENGG._AND_BIO-TECH_INDUSTRY_%29.pdf

This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.