Electronic Gate Security Alarm Assembly

—

Prepared on: 26 October 2026 · Prepared with Building Business DPR (buildingbusiness.in)

01 Project at a glance

Total project cost
₹1.58 L
Term loan from bank
₹1.02 L
Promoter’s contribution
₹0.16 L
Subsidy
₹0.39 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-3.17 L
Average DSCR
-14.35
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Assemble gate alarms that sound when someone crosses the gate of a house, office or campus.

Main product or serviceElectronic Gate Security Alarm Assembly
Installed capacity per year (at 100%)10,000 units

04 Market

  • Large houses and residential buildings
  • Commercial complexes and restricted establishments
  • Direct sale with installation
  • Electrical and security equipment dealers

05 Plant and machinery

ItemQty₹Total ₹
Portable drilling machine100
IC tester kit100
Test bench with instruments100
Work benches with power sockets (× 4)100
Digital multimeter, 3½ digit (× 3)100
Hand-operated 500 V DC megger (× 2)100
Digital milli-ohm meter100
Electrification and installation (10% of equipment), office furniture, shelves and racks (× 1 lot)11,50,0001,50,000
Total1,50,000

Pre-filled from: KVIC Project Profile — Electronic Gate Security System (PMEGP). Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Electronic components and PCBs for transmitter and receiver — raw material ₹5.80 lakh a year
  • 9 V batteries, alarm speakers, moulded PVC bases
  • Cartons, guarantee cards and manuals — packing ₹20,000 a year

07 Cost of project

₹ in lakh
Plant and machinery1.50
Contingency0.08
Total fixed capital1.58
Working capital margin0.00
Total project cost1.58

08 Means of finance

₹ in lakh%
Promoter’s contribution0.1610.0
Subsidy0.3925.0
Term loan from bank1.0265.0
Total1.58100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance0.030.030.030.030.030.030.03
Insurance0.010.010.010.010.010.010.01
Total cost of operations2.922.922.922.922.922.922.92
Operating profit (EBITDA)-2.92-2.92-2.92-2.92-2.92-2.92-2.92
Depreciation0.240.200.170.150.120.100.09
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan0.110.100.080.060.040.030.01
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-3.27-3.22-3.17-3.13-3.09-3.05-3.02
Income tax0.000.000.000.000.000.000.00
Profit after tax-3.27-3.22-3.17-3.13-3.09-3.05-3.02

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-3.27-3.22-3.17-3.13-3.09-3.05-3.02
Depreciation0.240.200.170.150.120.100.09
Cash accruals (PAT + depreciation)-3.03-3.02-3.00-2.98-2.96-2.95-2.93
Term loan repaid0.080.160.160.160.160.160.16
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-3.11-3.17-3.16-3.14-3.12-3.10-3.09
Cash and bank-3.11-6.28-9.44-12.58-15.70-18.80-21.89

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)0.550.550.550.550.550.550.55
Reserves and surplus-3.27-6.48-9.65-12.78-15.86-18.91-21.93
Term loan outstanding0.950.790.630.470.320.160.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities-1.77-5.14-8.47-11.75-15.00-18.21-21.38
Net fixed assets1.341.140.970.820.700.590.50
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-3.11-6.28-9.44-12.58-15.70-18.80-21.89
Total assets-1.77-5.14-8.47-11.75-15.00-18.21-21.38

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-15.40-11.52-12.36-13.34-14.49-15.85-17.49
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-14.35
Lowest DSCR-17.49
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation0.240.200.170.150.120.100.09

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
11.020.110.080.95
20.950.100.160.79
30.790.080.160.63
40.630.060.160.47
50.470.040.160.32
60.320.030.160.16
70.160.010.160.00

17 Licences and registrations

  • Udyam registration
  • GST registration
  • BIS certification if a Quality Control Order covers the product (check the BIS list)

18 Government schemes that may apply

  • Prime Minister's Employment Generation Programme (PMEGP)
  • Pradhan Mantri MUDRA Yojana (PMMY) – Shishu, Kishor, Tarun, Tarun Plus
  • Mukhyamantri Yuva Udyami Vikas Abhiyan (CM-YUVA)
  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)

19 Sources

  1. KVIC Project Profile — Electronic Gate Security System (PMEGP) — https://pmegp.msme.gov.in/Home/DownloadDocument?fileName=Documents/ProjectSampleReport/ELECTRONIC_GATE_SECURITY_SYSTEMS_%28_RURAL_ENGG._AND_BIO-TECH_INDUSTRY_%29.pdf