Detailed Project Report
LED Bulb Assembly Unit
—
Prepared on: 27 October 2026 · Prepared with Building Business DPR (buildingbusiness.in)
01 Project at a glance
- Total project cost
- ₹0.00 L
- Term loan from bank
- ₹0.00 L
- Promoter’s contribution
- ₹0.00 L
- Sales · Year 3
- ₹0.00 L
- Profit after tax · Year 3
- ₹-2.88 L
- Average DSCR
- —
- Break-even (% of capacity used)
- —
02 Promoter and unit
| Promoter name | — |
|---|---|
| Business / firm name | — |
| Legal form | Proprietorship |
| Address of the unit | — |
| Applicant category | General · Rural |
03 The project
Buy kits, assemble, test and sell under your own brand — work that fits a small space.
| Main product or service | LED Bulb Assembly Unit |
|---|---|
| Installed capacity per year (at 100%) | 10,000 units |
04 Market
- Households
- Shops and offices
- Contractors doing electrical work
- Electrical retail shops
- Electrical wholesalers
- Sale under your own brand
05 Plant and machinery
| Item | Qty | ₹ | Total ₹ |
|---|---|---|---|
| Total | 0 |
06 Raw materials
- LED chips — the light source of the bulb
- LED driver circuit — needed to run LEDs on mains power
- Packing material — the UP report budgets ₹1.26 lakh packing cost in year 1
07 Cost of project
| ₹ in lakh | |
|---|---|
| Total fixed capital | 0.00 |
| Working capital margin | 0.00 |
| Total project cost | 0.00 |
08 Means of finance
| ₹ in lakh | % | |
|---|---|---|
| Total | 0.00 | 100.0 |
| Working capital loan (outside project cost) | 0.00 |
09 Key assumptions
| Selling price | ₹0 per units |
|---|---|
| Raw material & packing cost | ₹0 per units |
| Capacity used each year | 60% · 70% · 80% · 80% · 80% · 80% · 80% |
| Term loan interest rate (% a year) | 11% · 84 months (Moratorium 6) |
| Working capital method | Turnover method (RBI) · Working capital interest (% a year) 11% |
| Income tax rate | 25% |
| Yearly price and cost rise | 0% |
10 Production and sales
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Capacity used | 60% | 70% | 80% | 80% | 80% | 80% | 80% |
| Production (units) | 6,000 | 7,000 | 8,000 | 8,000 | 8,000 | 8,000 | 8,000 |
| Sales | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
11 Projected profitability
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Sales | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Raw material and packing | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Power and fuel | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Salaries and wages | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 |
| Rent | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Administration | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Selling and distribution | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Repairs and maintenance | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Insurance | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Total cost of operations | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 |
| Operating profit (EBITDA) | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 |
| Depreciation | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Preliminary expenses written off | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Interest on term loan | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Interest on working capital | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Profit before tax | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 |
| Income tax | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Profit after tax | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 |
12 Cash flow
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Profit after tax | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 |
| Depreciation | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Cash accruals (PAT + depreciation) | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 |
| Term loan repaid | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Owner’s drawings | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Surplus after repayment | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 | -2.88 |
| Cash and bank | -2.88 | -5.76 | -8.64 | -11.52 | -14.40 | -17.28 | -20.16 |
13 Projected balance sheet
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Capital (own + subsidy) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Reserves and surplus | -2.88 | -5.76 | -8.64 | -11.52 | -14.40 | -17.28 | -20.16 |
| Term loan outstanding | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Working capital loan | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Total liabilities | -2.88 | -5.76 | -8.64 | -11.52 | -14.40 | -17.28 | -20.16 |
| Net fixed assets | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Preliminary expenses not written off | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Current assets (stock and debtors) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Cash and bank | -2.88 | -5.76 | -8.64 | -11.52 | -14.40 | -17.28 | -20.16 |
| Total assets | -2.88 | -5.76 | -8.64 | -11.52 | -14.40 | -17.28 | -20.16 |
14 Ratios and break-even
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Debt service coverage ratio (DSCR) | — | — | — | — | — | — | — |
| Break-even (% of capacity used) | — | — | — | — | — | — | — |
| Cash break-even | — | — | — | — | — | — | — |
| Average DSCR | — |
|---|---|
| Lowest DSCR | — |
| Payback period | — |
15 Depreciation
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Depreciation | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.
16 Term loan repayment
| Year | Opening | Interest | Term loan repaid | Closing |
|---|---|---|---|---|
| 1 | 0.00 | 0.00 | 0.00 | 0.00 |
| 2 | 0.00 | 0.00 | 0.00 | 0.00 |
| 3 | 0.00 | 0.00 | 0.00 | 0.00 |
| 4 | 0.00 | 0.00 | 0.00 | 0.00 |
| 5 | 0.00 | 0.00 | 0.00 | 0.00 |
| 6 | 0.00 | 0.00 | 0.00 | 0.00 |
| 7 | 0.00 | 0.00 | 0.00 | 0.00 |
17 Licences and registrations
- Udyam
- GST
- BIS registration (Compulsory Registration Scheme — LED lamps, IS 16102)
- E-waste (EPR) registration if you sell under your own brand
18 Government schemes that may apply
- Mukhyamantri Yuva Udyami Vikas Abhiyan (CM-YUVA)
- Pradhan Mantri MUDRA Yojana (PMMY) – Shishu, Kishor, Tarun, Tarun Plus
- Prime Minister's Employment Generation Programme (PMEGP)
- Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)
19 Sources
- UP MSME 1-Connect (Govt of UP, RAMP) – Project Report: LED Bulb — https://msme1connect.up.gov.in/Projectreport/Project%20Report638655579240290594.pdf
- DGFT Notification No. 54/2015-20 (9 Feb 2022) – ITC(HS) 2022, Annexure II (new and deleted codes) — https://content.dgft.gov.in/Website/dgftprod/7d5fd1eb-ad39-4c99-b760-014223657469/Eng-Notification%2054%20dated%209%20Feb%202022%20ITC(HS)%202022%20_with%20Annexures.pdf
This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.