01 Project at a glance
- Total project cost
- ₹0.58 L
- Term loan from bank
- ₹0.38 L
- Promoter’s contribution
- ₹0.06 L
- Subsidy
- ₹0.14 L
- Sales · Year 3
- ₹0.00 L
- Profit after tax · Year 3
- ₹-2.99 L
- Average DSCR
- -38.80
- Break-even (% of capacity used)
- —
02 Promoter and unit
| Promoter name | — |
|---|---|
| Business / firm name | — |
| Legal form | Proprietorship |
| Address of the unit | — |
| Applicant category | General · Rural |
03 The project
Cut and weld PVC sheet into folders and files for schools, offices and banks.
| Main product or service | PVC Plastic Folders and Files |
|---|---|
| Installed capacity per year (at 100%) | 10,000 units |
04 Market
- Schools and colleges
- Government offices
- Banks and financial institutions
- Companies (printed publicity folders)
- Bookshops and stationery stores
- Fancy stores in towns
- Direct bulk orders
05 Plant and machinery
| Item | Qty | ₹ | Total ₹ |
|---|---|---|---|
| Plastic welding machine, 100 W | 1 | 50,000 | 50,000 |
| Screen-printing equipment | 1 | 5,000 | 5,000 |
| Total | 55,000 |
Pre-filled from: DC-MSME project profile — Plastic Folders (PMRY series); World Customs Organization – HS Nomenclature 2022, Chapter 39. Prices in older reports will have gone up — enter today’s quotations.
06 Raw materials
- PVC sheet rolls (0.20 mm and 0.175 mm) — ₹20,313 a month in the profile
- PVC tubes / U-shaped profiles (0.12 mm and 0.15 mm) — ₹6,770 a month in the profile
07 Cost of project
| ₹ in lakh | |
|---|---|
| Plant and machinery | 0.55 |
| Contingency | 0.03 |
| Total fixed capital | 0.58 |
| Working capital margin | 0.00 |
| Total project cost | 0.58 |
08 Means of finance
| ₹ in lakh | % | |
|---|---|---|
| Promoter’s contribution | 0.06 | 10.0 |
| Subsidy | 0.14 | 25.0 |
| Term loan from bank | 0.38 | 65.0 |
| Total | 0.58 | 100.0 |
| Working capital loan (outside project cost) | 0.00 |
09 Key assumptions
| Selling price | ₹0 per units |
|---|---|
| Raw material & packing cost | ₹0 per units |
| Capacity used each year | 60% · 70% · 80% · 80% · 80% · 80% · 80% |
| Term loan interest rate (% a year) | 11% · 84 months (Moratorium 6) |
| Working capital method | Turnover method (RBI) · Working capital interest (% a year) 11% |
| Income tax rate | 25% |
| Yearly price and cost rise | 0% |
10 Production and sales
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Capacity used | 60% | 70% | 80% | 80% | 80% | 80% | 80% |
| Production (units) | 6,000 | 7,000 | 8,000 | 8,000 | 8,000 | 8,000 | 8,000 |
| Sales | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
11 Projected profitability
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Sales | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Raw material and packing | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Power and fuel | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Salaries and wages | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 | 2.88 |
| Rent | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Administration | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Selling and distribution | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Repairs and maintenance | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 | 0.01 |
| Insurance | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Total cost of operations | 2.89 | 2.89 | 2.89 | 2.89 | 2.89 | 2.89 | 2.89 |
| Operating profit (EBITDA) | -2.89 | -2.89 | -2.89 | -2.89 | -2.89 | -2.89 | -2.89 |
| Depreciation | 0.09 | 0.07 | 0.06 | 0.05 | 0.05 | 0.04 | 0.03 |
| Preliminary expenses written off | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Interest on term loan | 0.04 | 0.04 | 0.03 | 0.02 | 0.02 | 0.01 | 0.00 |
| Interest on working capital | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Profit before tax | -3.02 | -3.00 | -2.99 | -2.97 | -2.96 | -2.94 | -2.93 |
| Income tax | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Profit after tax | -3.02 | -3.00 | -2.99 | -2.97 | -2.96 | -2.94 | -2.93 |
12 Cash flow
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Profit after tax | -3.02 | -3.00 | -2.99 | -2.97 | -2.96 | -2.94 | -2.93 |
| Depreciation | 0.09 | 0.07 | 0.06 | 0.05 | 0.05 | 0.04 | 0.03 |
| Cash accruals (PAT + depreciation) | -2.94 | -2.93 | -2.92 | -2.92 | -2.91 | -2.90 | -2.90 |
| Term loan repaid | 0.03 | 0.06 | 0.06 | 0.06 | 0.06 | 0.06 | 0.06 |
| Owner’s drawings | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Surplus after repayment | -2.96 | -2.99 | -2.98 | -2.97 | -2.97 | -2.96 | -2.96 |
| Cash and bank | -2.96 | -5.95 | -8.93 | -11.91 | -14.88 | -17.84 | -20.79 |
13 Projected balance sheet
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Capital (own + subsidy) | 0.20 | 0.20 | 0.20 | 0.20 | 0.20 | 0.20 | 0.20 |
| Reserves and surplus | -3.02 | -6.02 | -9.01 | -11.98 | -14.94 | -17.88 | -20.81 |
| Term loan outstanding | 0.35 | 0.29 | 0.23 | 0.17 | 0.12 | 0.06 | 0.00 |
| Working capital loan | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Total liabilities | -2.47 | -5.53 | -8.58 | -11.61 | -14.62 | -17.62 | -20.61 |
| Net fixed assets | 0.49 | 0.42 | 0.35 | 0.30 | 0.26 | 0.22 | 0.19 |
| Preliminary expenses not written off | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Current assets (stock and debtors) | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 |
| Cash and bank | -2.96 | -5.95 | -8.93 | -11.91 | -14.88 | -17.84 | -20.79 |
| Total assets | -2.47 | -5.53 | -8.58 | -11.61 | -14.62 | -17.62 | -20.61 |
14 Ratios and break-even
| Year | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Debt service coverage ratio (DSCR) | -41.64 | -31.14 | -33.42 | -36.07 | -39.17 | -42.85 | -47.30 |
| Break-even (% of capacity used) | — | — | — | — | — | — | — |
| Cash break-even | — | — | — | — | — | — | — |
| Average DSCR | -38.80 |
|---|---|
| Lowest DSCR | -47.30 |
| Payback period | — |
15 Depreciation
| Year → (₹ in lakh) | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
|---|---|---|---|---|---|---|---|
| Depreciation | 0.09 | 0.07 | 0.06 | 0.05 | 0.05 | 0.04 | 0.03 |
Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.
16 Term loan repayment
| Year | Opening | Interest | Term loan repaid | Closing |
|---|---|---|---|---|
| 1 | 0.38 | 0.04 | 0.03 | 0.35 |
| 2 | 0.35 | 0.04 | 0.06 | 0.29 |
| 3 | 0.29 | 0.03 | 0.06 | 0.23 |
| 4 | 0.23 | 0.02 | 0.06 | 0.17 |
| 5 | 0.17 | 0.02 | 0.06 | 0.12 |
| 6 | 0.12 | 0.01 | 0.06 | 0.06 |
| 7 | 0.06 | 0.00 | 0.06 | 0.00 |
17 Licences and registrations
- Udyam registration
- GST registration
- Trade licence from the local body
18 Government schemes that may apply
- Prime Minister's Employment Generation Programme (PMEGP)
- Pradhan Mantri MUDRA Yojana (PMMY) – Shishu, Kishor, Tarun, Tarun Plus
19 Sources
- DC-MSME project profile — Plastic Folders (PMRY series) — https://www.dcmsme.gov.in/publications/pmryprof/chem/ch22.pdf
- World Customs Organization – HS Nomenclature 2022, Chapter 39 — https://www.wcoomd.org/-/media/wco/public/global/pdf/topics/nomenclature/instruments-and-tools/hs-nomenclature-2022/2022/0739_2022e.pdf
This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.