Detailed Project Report

Cast Iron Brake Drums (Small Foundry)

—

Prepared on: 13 November 2026 · Prepared with Building Business DPR (buildingbusiness.in)

01 Project at a glance

Total project cost
₹4.25 L
Term loan from bank
₹2.76 L
Promoter’s contribution
₹0.43 L
Subsidy
₹1.06 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-3.66 L
Average DSCR
-5.44
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Cast iron brake drums for two-wheelers in a small foundry with an oil-fired rotary furnace and sand moulding.

Main product or serviceCast Iron Brake Drums (Small Foundry)
Installed capacity per year (at 100%)10,000 units

04 Market

  • Two-wheeler makers and their suppliers
  • Spare-parts dealers and garages
  • Direct supply to vehicle-part makers
  • Auto spare-parts wholesalers

05 Plant and machinery

ItemQty₹Total ₹
Oil-fired rotary furnace100
Sand muller and mixer100
Vibrating sieve machine100
Hand-operated pin-lift moulding machine100
Core and mould drying oven100
Platform weighing machine100
Flexible shaft grinder100
Drilling machine100
Double-ended pedestal grinder100
Air compressor100
Gear pump for furnace oil100
Cast iron / fabricated plate mould boxes, patterns and foundry tools100
Electrical installation and office equipment100
Equipment total14,05,0004,05,000
Total4,05,000

Pre-filled from: KVIC Project Profile — Cast Iron Brake Drums (PMEGP). Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Metal for casting (not itemised in the profile) — raw material ₹72.00 lakh a year at full capacity
  • Furnace oil — for the oil-fired rotary furnace
  • Moulding sand and cores
  • Packing material — ₹25,000 a year

07 Cost of project

₹ in lakh
Plant and machinery4.05
Contingency0.20
Total fixed capital4.25
Working capital margin0.00
Total project cost4.25

08 Means of finance

₹ in lakh%
Promoter’s contribution0.4310.0
Subsidy1.0625.0
Term loan from bank2.7665.0
Total4.25100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance0.090.090.090.090.090.090.09
Insurance0.020.020.020.020.020.020.02
Total cost of operations2.992.992.992.992.992.992.99
Operating profit (EBITDA)-2.99-2.99-2.99-2.99-2.99-2.99-2.99
Depreciation0.640.540.460.390.330.280.24
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan0.300.260.210.170.120.070.03
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-3.92-3.79-3.66-3.54-3.44-3.34-3.25
Income tax0.000.000.000.000.000.000.00
Profit after tax-3.92-3.79-3.66-3.54-3.44-3.34-3.25

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-3.92-3.79-3.66-3.54-3.44-3.34-3.25
Depreciation0.640.540.460.390.330.280.24
Cash accruals (PAT + depreciation)-3.29-3.25-3.20-3.15-3.11-3.06-3.01
Term loan repaid0.210.430.430.430.430.430.43
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-3.50-3.67-3.62-3.58-3.53-3.48-3.44
Cash and bank-3.50-7.17-10.79-14.37-17.90-21.38-24.82

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)1.491.491.491.491.491.491.49
Reserves and surplus-3.92-7.71-11.37-14.91-18.35-21.69-24.95
Term loan outstanding2.552.131.701.280.850.430.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities0.12-4.10-8.18-12.15-16.01-19.78-23.46
Net fixed assets3.613.072.612.221.891.601.36
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-3.50-7.17-10.79-14.37-17.90-21.38-24.82
Total assets0.12-4.10-8.18-12.15-16.01-19.78-23.46

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-5.83-4.36-4.68-5.05-5.49-6.00-6.63
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-5.44
Lowest DSCR-6.63
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation0.640.540.460.390.330.280.24

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
12.760.300.212.55
22.550.260.432.13
32.130.210.431.70
41.700.170.431.28
51.280.120.430.85
60.850.070.430.43
70.430.030.430.00

17 Licences and registrations

  • Udyam
  • GST
  • Pollution Control Board consent (foundries are on the polluting list — check your state's category)
  • Factory licence
  • Fire safety NOC

18 Government schemes that may apply

  • Prime Minister's Employment Generation Programme (PMEGP)
  • Pradhan Mantri MUDRA Yojana (PMMY) – Shishu, Kishor, Tarun, Tarun Plus
  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)

19 Sources

  1. KVIC Project Profile — Cast Iron Brake Drums (PMEGP) — https://pmegp.msme.gov.in/Home/DownloadDocument?fileName=Documents/ProjectSampleReport/CAST_IRON_BRAKE_DRUMS_%28_RURAL_ENGG._AND_BIO-TECH_INDUSTRY_%29.pdf

This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.