01 Project at a glance

Total project cost
₹22.05 L
Term loan from bank
₹19.85 L
Promoter’s contribution
₹2.21 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-7.35 L
Average DSCR
-0.87
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Dressing live broiler birds, cutting, blast-freezing and vacuum-packing chicken for shops, hotels and caterers.

Main product or serviceFrozen Chicken Processing Unit
Installed capacity per year (at 100%)10,000 units

04 Market

  • Hotels, restaurants and caterers
  • Retail chains and frozen-food shops
  • Households
  • Direct supply to hotels and caterers
  • Distributors with freezer vans
  • Own retail counter

05 Plant and machinery

ItemQty₹Total ₹
Chicken cutting machine130,00030,000
Chicken scalding tank133,00033,000
Chicken feather cleaning machine122,00022,000
Chicken head puller155,00055,000
Blast freezer18,50,0008,50,000
Cold chamber14,60,0004,60,000
Vacuum packaging machine14,00,0004,00,000
Other equipment (washing tanks, hook conveyor, knives, trolleys, bins)12,50,0002,50,000
Total21,00,000

Pre-filled from: NIFTEM-Thanjavur (IIFPT) PMFME model DPR — Frozen Chicken. Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Live broiler birds — taken at ₹120 a kg in the report; bought from poultry farms
  • Vacuum pouches and cartons — packing material

07 Cost of project

₹ in lakh
Plant and machinery21.00
Contingency1.05
Total fixed capital22.05
Working capital margin0.00
Total project cost22.05

08 Means of finance

₹ in lakh%
Promoter’s contribution2.2110.0
Term loan from bank19.8590.0
Total22.05100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance0.440.440.440.440.440.440.44
Insurance0.110.110.110.110.110.110.11
Total cost of operations3.433.433.433.433.433.433.43
Operating profit (EBITDA)-3.43-3.43-3.43-3.43-3.43-3.43-3.43
Depreciation3.312.812.392.031.731.471.25
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan2.151.861.531.190.850.520.18
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-8.89-8.10-7.35-6.65-6.01-5.42-4.86
Income tax0.000.000.000.000.000.000.00
Profit after tax-8.89-8.10-7.35-6.65-6.01-5.42-4.86

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-8.89-8.10-7.35-6.65-6.01-5.42-4.86
Depreciation3.312.812.392.031.731.471.25
Cash accruals (PAT + depreciation)-5.58-5.29-4.96-4.62-4.28-3.95-3.61
Term loan repaid1.533.053.053.053.053.053.05
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-7.11-8.35-8.01-7.67-7.34-7.00-6.67
Cash and bank-7.11-15.45-23.46-31.13-38.47-45.47-52.14

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)2.212.212.212.212.212.212.21
Reserves and surplus-8.89-16.99-24.34-30.99-37.00-42.42-47.28
Term loan outstanding18.3215.2712.219.166.113.050.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities11.640.48-9.92-19.62-28.69-37.16-45.07
Net fixed assets18.7415.9313.5411.519.788.327.07
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-7.11-15.45-23.46-31.13-38.47-45.47-52.14
Total assets11.640.48-9.92-19.62-28.69-37.16-45.07

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-0.93-0.70-0.75-0.81-0.88-0.96-1.06
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-0.87
Lowest DSCR-1.06
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation3.312.812.392.031.731.471.25

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
119.852.151.5318.32
218.321.863.0515.27
315.271.533.0512.21
412.211.193.059.16
59.160.853.056.11
66.110.523.053.05
73.050.183.050.00

17 Licences and registrations

  • Udyam registration
  • GST registration
  • FSSAI licence (meat processing)
  • Trade licence and slaughter permission from the local body
  • Consent from the State Pollution Control Board

18 Government schemes that may apply

  • PM Formalisation of Micro Food Processing Enterprises (PM FME)
  • Pradhan Mantri MUDRA Yojana (PMMY) – Shishu, Kishor, Tarun, Tarun Plus
  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)

19 Sources

  1. NIFTEM-Thanjavur (IIFPT) PMFME model DPR — Frozen Chicken — https://niftem-t.ac.in/pmfme/dpr-fchicken.pdf

This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.