Building BusinessServices

Section 24

Mosquito Repellent Mat

Fill six short steps; the report updates as you type. Print it or save it as a PDF when you are done. Published project reports put the total cost of this business between ₹28.21 lakh and ₹28.21 lakh.

Legal form
Applicant category
Location

Detailed Project Report

Mosquito Repellent Mat

—

Prepared on: 13 November 2026 · Prepared with Building Business DPR (buildingbusiness.in)

01 Project at a glance

Total project cost
₹8.09 L
Term loan from bank
₹5.26 L
Promoter’s contribution
₹0.81 L
Subsidy
₹2.02 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-4.36 L
Average DSCR
-2.95
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Soak absorbent paper mats in an allethrin-based repellent, dry and pack them for electric mat heaters.

Main product or serviceMosquito Repellent Mat
Installed capacity per year (at 100%)10,000 units

04 Market

  • Households, through kirana and general stores
  • Hotels, hostels and institutions
  • Distributors and wholesalers
  • Own delivery staff to retailers (two delivery men in the report)

05 Plant and machinery

ItemQty₹Total ₹
Tablet punching machine, 30 T185,00085,000
Shearing machine110,00010,000
Strapping machine145,00045,000
Laboratory — gas chromatograph with printer12,30,0002,30,000
Automatic impregnation / sealing unit14,00,0004,00,000
Mechanical formulation and storage unit, weighing machine (100 kg), hand pump, precision balance (× 1 each)100
Total7,70,000

Pre-filled from: DC-MSME project profile — Mosquito Repellent Mat; World Customs Organization – HS Nomenclature 2022, Chapter 38. Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Synthetic pyrethroid (allethrin), technical grade — 50 kg a month at ₹6,650 a kg in the report
  • Piperonyl butoxide (PBO) — 30 kg a month at ₹725 a kg
  • Absorbent paper / cellulose sheets — 1,000 kg a month at ₹70 a kg
  • Perfume and dye — 8 kg perfume, 2 kg dye a month
  • Printed polythene and laminated board cartons — packing for 9,000 boxes a month

07 Cost of project

₹ in lakh
Plant and machinery7.70
Contingency0.39
Total fixed capital8.09
Working capital margin0.00
Total project cost8.09

08 Means of finance

₹ in lakh%
Promoter’s contribution0.8110.0
Subsidy2.0225.0
Term loan from bank5.2665.0
Total8.09100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance0.160.160.160.160.160.160.16
Insurance0.040.040.040.040.040.040.04
Total cost of operations3.083.083.083.083.083.083.08
Operating profit (EBITDA)-3.08-3.08-3.08-3.08-3.08-3.08-3.08
Depreciation1.211.030.880.740.630.540.46
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan0.570.490.400.310.230.140.05
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-4.86-4.61-4.36-4.14-3.94-3.76-3.59
Income tax0.000.000.000.000.000.000.00
Profit after tax-4.86-4.61-4.36-4.14-3.94-3.76-3.59

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-4.86-4.61-4.36-4.14-3.94-3.76-3.59
Depreciation1.211.030.880.740.630.540.46
Cash accruals (PAT + depreciation)-3.65-3.57-3.49-3.40-3.31-3.22-3.13
Term loan repaid0.400.810.810.810.810.810.81
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-4.06-4.38-4.29-4.21-4.12-4.03-3.94
Cash and bank-4.06-8.44-12.73-16.94-21.06-25.08-29.02

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)2.832.832.832.832.832.832.83
Reserves and surplus-4.86-9.47-13.83-17.97-21.91-25.67-29.26
Term loan outstanding4.854.043.232.431.620.810.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities2.82-2.60-7.77-12.72-17.47-22.03-26.43
Net fixed assets6.875.844.974.223.593.052.59
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-4.06-8.44-12.73-16.94-21.06-25.08-29.02
Total assets2.82-2.60-7.77-12.72-17.47-22.03-26.43

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-3.17-2.37-2.54-2.74-2.98-3.26-3.60
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-2.95
Lowest DSCR-3.60
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation1.211.030.880.740.630.540.46

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
15.260.570.404.85
24.850.490.814.04
34.040.400.813.23
43.230.310.812.43
52.430.230.811.62
61.620.140.810.81
70.810.050.810.00

17 Licences and registrations

  • Udyam registration
  • GST registration
  • Registration of the product with the Central Insecticides Board and Registration Committee (CIB&RC) under the Insecticides Act, 1968
  • State manufacturing licence for insecticides from the state agriculture department
  • Legal Metrology registration for packaged goods

18 Government schemes that may apply

  • Prime Minister's Employment Generation Programme (PMEGP)
  • Pradhan Mantri MUDRA Yojana (PMMY) – Shishu, Kishor, Tarun, Tarun Plus
  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)
  • Stand-Up India

19 Sources

  1. DC-MSME project profile — Mosquito Repellent Mat — https://www.dcmsme.gov.in/publications/pmryprof/chemical/ch17.pdf
  2. World Customs Organization – HS Nomenclature 2022, Chapter 38 — https://www.wcoomd.org/-/media/wco/public/global/pdf/topics/nomenclature/instruments-and-tools/hs-nomenclature-2022/2022/0638_2022e.pdf

This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.