01 Project at a glance

Total project cost
₹59.33 L
Term loan from bank
₹53.39 L
Promoter’s contribution
₹5.93 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-14.90 L
Average DSCR
-0.41
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Chrome-tan heavy buffalo hides and print them with a zuggrain pattern to make upper leather for safety shoes and boots.

Main product or serviceZuggrain Leather Tannery (Safety Shoe Upper Leather)
Installed capacity per year (at 100%)10,000 units

04 Market

  • Safety shoe and boot manufacturers
  • Suppliers to defence, paramilitary forces and NCC
  • Shoe upper makers and leather exporters
  • Direct sale to footwear factories by grade and area
  • Leather merchants in tannery clusters
  • Export orders for leather and uppers

05 Plant and machinery

ItemQty₹Total ₹
Wooden paddle vats 8 × 8 ft with 10 HP motor (× 4)14,00,0004,00,000
Tanning drums with 10 HP motor (× 3)16,00,0006,00,000
Fleshing machine 2,700 mm with 40 HP motor15,00,0005,00,000
Shaving machine 12 inch, 7.5 HP12,00,0002,00,000
Setting-out machine 2,000 mm, 25 HP13,00,0003,00,000
Splitting machine 2,700 mm with 25 HP motor (imported)115,00,00015,00,000
Slow comb staking machine, 5 HP11,00,0001,00,000
Buffing machine, 5 HP11,00,0001,00,000
Spray booth with gun and air compressor11,00,0001,00,000
Weighing scales (500 kg, 100 kg, 5 kg) (× 3)150,00050,000
Diesel generating set 50 kVA13,00,0003,00,000
Effluent treatment plant with chrome recovery (estimate, listed separately)115,00,00015,00,000
Total56,50,000

Pre-filled from: DC-MSME project profile — Zuggrain Leather. Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Wet salted buffalo hides, about 20 kg and 40 sq ft each — 2,500 a month at ₹1,200 a piece = ₹30,00,000
  • Tanning, dyeing and finishing chemicals — ₹15 per sq ft = ₹15,00,000 a month

07 Cost of project

₹ in lakh
Plant and machinery56.50
Contingency2.83
Total fixed capital59.33
Working capital margin0.00
Total project cost59.33

08 Means of finance

₹ in lakh%
Promoter’s contribution5.9310.0
Term loan from bank53.3990.0
Total59.33100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance1.191.191.191.191.191.191.19
Insurance0.300.300.300.300.300.300.30
Total cost of operations4.364.364.364.364.364.364.36
Operating profit (EBITDA)-4.36-4.36-4.36-4.36-4.36-4.36-4.36
Depreciation8.907.566.435.464.653.953.36
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan5.785.014.103.202.301.390.49
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-19.04-16.93-14.90-13.03-11.30-9.70-8.21
Income tax0.000.000.000.000.000.000.00
Profit after tax-19.04-16.93-14.90-13.03-11.30-9.70-8.21

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-19.04-16.93-14.90-13.03-11.30-9.70-8.21
Depreciation8.907.566.435.464.653.953.36
Cash accruals (PAT + depreciation)-10.14-9.37-8.47-7.56-6.66-5.76-4.85
Term loan repaid4.118.218.218.218.218.218.21
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-14.25-17.58-16.68-15.78-14.87-13.97-13.07
Cash and bank-14.25-31.83-48.51-64.29-79.17-93.14-106.20

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)5.935.935.935.935.935.935.93
Reserves and surplus-19.04-35.98-50.87-63.90-75.20-84.91-93.12
Term loan outstanding49.2941.0732.8624.6416.438.210.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities36.1811.03-12.08-33.32-52.84-70.76-87.19
Net fixed assets50.4342.8636.4330.9726.3222.3719.02
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-14.25-31.83-48.51-64.29-79.17-93.14-106.20
Total assets36.1811.03-12.08-33.32-52.84-70.76-87.19

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-0.44-0.33-0.35-0.38-0.42-0.45-0.50
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-0.41
Lowest DSCR-0.50
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation8.907.566.435.464.653.953.36

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
153.395.784.1149.29
249.295.018.2141.07
341.074.108.2132.86
432.863.208.2124.64
524.642.308.2116.43
616.431.398.218.21
78.210.498.210.00

17 Licences and registrations

  • Udyam registration
  • GST registration
  • Factory licence
  • Consent to establish and operate from the State Pollution Control Board (tanneries are a highly polluting category)
  • Hazardous waste authorisation for chrome sludge
  • Membership of a common effluent treatment plant, or your own ETP

18 Government schemes that may apply

  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)

19 Sources

  1. DC-MSME project profile — Zuggrain Leather — https://www.dcmsme.gov.in/old/reports/leather/zuggrainleather.pdf