§1What this business is

Metal items are cleaned of dirt and oil, rinsed, etched in sulphuric acid, rinsed again, nickel-plated for 10–15 minutes, rinsed, then chrome-plated in a chromic-acid bath, washed, dried and packed. The report's product is chrome plating of metal kitchen baskets. Buyers are kitchen-fittings makers, hardware and furniture makers, and auto-parts units.

Capacity: 500 units a day on a 10-hour shift; year 1 at 50%.

§2Is it right for you?

Who it is for

Someone with electroplating experience in an industrial area with job-work demand.

Who it is not for

Someone who cannot invest in effluent treatment and safety.

Advantages

  • Kitchen, furniture, auto and hardware makers all need plating
  • Machinery is tanks, rectifiers and busbars — under ₹7.5 lakh
  • Can work as job-work for many local makers
  • Chrome finish adds value and corrosion resistance

Drawbacks

  • Hexavalent chromium and acids are hazardous — effluent treatment is a must
  • Pollution boards treat electroplating as a highly polluting activity
  • Net margin is only 4.7–6.0%
  • Break-even is high at 45%

Skills you need

  • Bath chemistry and plating thickness control
  • Rectifier and current control
  • Effluent treatment
  • Job-work sales

Why difficulty 4/5: Hazardous chemistry and strict pollution compliance.

§3Market

Who buys

  • Kitchen-fittings and basket makers
  • Hardware and furniture makers
  • Automotive parts units

How it sells

  • Job-work orders from local manufacturers
  • Direct supply of plated products to dealers

Good to know

  • The report links demand to rising use of metal consumer goods and electroplating in automotive, aerospace and defence.

§4Raw material & machinery

ItemQtyCost
Nickel tank, PP 10 mm, 10′ × 2.5′ × 2.5′1₹42,000
Nickel filter1₹28,000
Air pump, 1 HP1₹17,500
Rectifier, 800 A, oil-cooled1₹1,55,000
Titanium baskets20₹30,000
Nickel tank busbar set1₹45,000
Nickel heaters (₹3,500 each)2₹7,000
Soaking tank, PP 10 mm, 3′ × 2.5′ × 2.5′1₹17,500
Anodic cleaning tank, PP 10 mm, 3′ × 2.5′ × 2.5′1₹17,500
Anodic busbar set1₹25,000
Rectifier, 300 A, 12 V, oil-cooled1₹68,000
Heater1₹3,500
Chrome tank, 3′ × 2.5′ × 2.5′ (MS 3 mm with PVC and FRP lining)1₹32,500
Rectifier, 600 A, 16 V, oil-cooled1₹1,25,000
Chrome busbar set1₹25,000
Chrome anodes (₹4,000 each)8₹32,000
Heater1₹4,500
Hot dryer, 50 kg capacity1₹69,000

From: PMEGP sample project report — Chrome Plating (prepared by Udyami/Samadhan)

  • Metal cleaners and acidscleaning and etching
  • Chromium trioxide and nickel sulphateplating baths; raw material ₹37.50 lakh in year 1
  • Plating chemicals and catalystsbath additives
  • Lead anodes, busbars and demineralised waterprocess consumables

From: PMEGP sample project report — Chrome Plating (prepared by Udyami/Samadhan)

§5Licences & registration

  1. Pollution control board consent to establish and operate (electroplating)
  2. Hazardous waste authorisation
  3. Udyam
  4. GST
  5. Factory licence
  6. Fire NOC
  7. Trade licence

We can do this registration for you

§6Schemes & subsidies

PMEGP sample project; MUDRA (up to ₹20 L) and CGTMSE fit the ₹12.87 L size.

§7Money

How the investment is worked out: Samadhan report: plant & machinery ₹7.44 L + furniture ₹0.80 L + working capital ₹4.63 L = ₹12.87 L. Premises own or rented. Finance: term loan ₹7.42 L, WC loan ₹4.17 L, own ₹1.29 L. (The PMEGP list also shows ₹15.44 L against the same file.)

Working capital: Working capital ₹4.63 lakh, bank finance ₹4.17 lakh — 10 days of stock, 15 days' credit both ways.

Year not printed on the report — check current machinery prices.

How to prepare a loan file

§8Export potential

Plating is a service; exports are of the plated product, under that product's own HS line.

§9Risks — where people fail

  • Pollution-board closure for poor effluent handling
  • Worker health hazards
  • Chemical price rise
  • Rejections for poor finish

§1030 / 60 / 90-day plan

A general plan that applies to any business. A plan for this business will be added after research.

  1. Days 1–30: Visit a working chrome plating unit unit, ask 10 buyers about price and quantity, and get quotations from 3 suppliers.
  2. Days 31–60: Udyam and the licences you need (Pollution control board consent to establish and operate (electroplating), Hazardous waste authorisation), a project report (DPR), and the scheme or loan file.
  3. Days 61–90: Space and machines, trial production, and first deliveries to 10 customers.

§11Who to connect with

Not verified yet

Associations, clusters and training institutes — the directory is being built. Connect

§12Watch

There is no episode on this business yet. Shows are coming soon on the Podcast page.

Want to start Chrome Plating Unit?

DPR, loan file or registration — ask us on WhatsApp.

Get a DPR / loan file made

Sources

  1. PMEGP sample project report — Chrome Plating (prepared by Udyami/Samadhan)

Data review: 6 October 2026. Spotted a mistake? Report it. For information only — not legal or financial advice.