§1What this business is

Metal sheet is fed, coiled into a rim band, flattened, butt-welded, trimmed, flared, roll-formed and flanged. The rim is then expanded, tested for air-tightness, the valve hole is punched and the disc is pressed in. The report names aluminium sheet as the raw material. Buyers are vehicle makers, their suppliers and the spare-parts (replacement) market.

Capacity: 160 rims a day on a 10-hour shift; year 1 planned at 50%.

§2Is it right for you?

Who it is for

Someone from an auto-parts or sheet-metal background with contacts among vehicle or spare-parts buyers.

Who it is not for

A first-time founder with no engineering staff — weld and size faults make rims unsafe.

Advantages

  • Every vehicle needs rims, and bent or worn rims are replaced
  • One machine line takes the job from sheet to finished rim
  • The report shows margin rising from 5.1% to 14.2% over five years

Drawbacks

  • Rims are a safety part — buyers demand strict testing
  • Machinery takes ₹18.35 L of the ₹23.28 L project cost
  • Large makers dominate; a small unit must find a niche such as replacement rims

Skills you need

  • Sheet-metal forming and welding
  • Size checks and air-tightness testing
  • Selling to vehicle makers and spare-parts dealers

Why difficulty 4/5: A safety part with costly machines and demanding buyers.

§3Market

Who buys

  • Vehicle and two-wheeler makers and their suppliers
  • Spare-parts dealers serving the replacement market

How it sells

  • Supply contracts with vehicle and component makers
  • Auto spare-parts wholesalers

Good to know

  • The report links demand to growth in vehicle sales.
  • Year-1 sales in the report are ₹58.00 L at 50% capacity.

§4Raw material & machinery

ItemQtyCost
Feeding machine1₹2,00,000
Rim band coiling machine1₹2,40,000
Flattening machine1₹1,80,000
Butt welding machine1₹52,000
Trimming, planishing and end-cutting machine1₹3,95,000
Horizontal flaring machine1₹1,00,000
Roll forming machine1₹3,00,000
Edge flanging machine1₹68,000
Expanding, gas-tightness testing and valve-hole punching machine1₹1,50,000
Press for fitting the disc into the rim1₹1,00,000
Welding machine1₹50,000

From: PMEGP sample project report — Wheel Rim (prepared by Udyami/Samadhan)

  • Aluminium metal sheetthe only major raw material named in the report

From: PMEGP sample project report — Wheel Rim (prepared by Udyami/Samadhan)

§5Licences & registration

  1. Udyam registration
  2. GST registration
  3. State Pollution Control Board consent to establish and operate, where the state requires it
  4. Factory licence if your worker count crosses the Factories Act limit
  5. BIS certification if a Quality Control Order covers the rim type you make — check with BIS

We can do this registration for you

§6Schemes & subsidies

PMEGP fits (manufacturing project of ₹23.28 L, under the ₹50 L limit); MUDRA up to ₹20 L; CGTMSE for a loan without collateral; Stand-Up India for SC/ST and women founders.

§7Money

How the investment is worked out: Plant & machinery ₹18.35 L + furniture & fixtures ₹1.00 L + working capital ₹3.93 L = ₹23.28 L. Land own or rented (not costed).

Working capital: Working capital ₹3.93 L, of which bank finance ₹3.54 L; 10 days of raw material and finished stock, 10 days' credit to buyers.

Year not printed on the report — check current machinery prices.

How to prepare a loan file

§8Export potential

Confirm the HS code in the DGFT ITC(HS) lookup before you export

8708.70Road wheels and parts and accessories thereof

Export council / board: EEPC India

  • Confirm the 8-digit ITC(HS) line with DGFT or your customs broker before shipping.
  • You need an Import Export Code (IEC) from DGFT before the first shipment.

§9Risks — where people fail

  • Whole batches rejected for poor welds or out-of-round rims
  • Metal price swings
  • Dependence on a few large buyers who pay late

§1030 / 60 / 90-day plan

A general plan that applies to any business. A plan for this business will be added after research.

  1. Days 1–30: Visit a working wheel rim manufacturing unit, ask 10 buyers about price and quantity, and get quotations from 3 suppliers.
  2. Days 31–60: Udyam and the licences you need (Udyam registration, GST registration), a project report (DPR), and the scheme or loan file.
  3. Days 61–90: Space and machines, trial production, and first deliveries to 10 customers.

§11Who to connect with

Not verified yet

Associations, clusters and training institutes — the directory is being built. Connect

§12Watch

There is no episode on this business yet. Shows are coming soon on the Podcast page.

Want to start Wheel Rim Manufacturing?

DPR, loan file or registration — ask us on WhatsApp.

Get a DPR / loan file made

Sources

  1. PMEGP sample project report — Wheel Rim (prepared by Udyami/Samadhan)

Data review: 6 October 2026. Spotted a mistake? Report it. For information only — not legal or financial advice.