§1Who it is for
- Large fully / partially integrated solar PV module manufacturers
Useful if
Solar EPC firms and component suppliers looking for domestic module sources.
Do not spend time on it if
Anyone wanting to apply — tranches are fully awarded.
§2Eligibility
- Selected through transparent bidding by IREDA (Tranche-I) and SECI (Tranche-II); bid conditions in tender documents — see the official guideline.
§3Benefits
- PLI for five years after commissioning, on manufacture and sale of high-efficiency solar PV modules.
§4Norms — pattern of assistance
- Tranche-I outlay ₹4,500 crore; Tranche-II ₹19,500 crore (total ₹24,000 crore).
- Target ~48 GW fully integrated capacity; investment commitments of nearly ₹52,942 crore (PIB Feb 2026).
§5Documents
The guideline does not list the documents. Ask the portal or bank before you apply — we do not make up lists.
§6How to apply
- 1
Closed — capacity fully allotted through bids.
§7Pros and cons
Merits
- Targets 48 GW of fully integrated capacity with investment commitments of nearly ₹52,942 crore (PIB Feb 2026).
- Domestic module supply helps solar EPC firms and component suppliers.
Demerits
- Bid-based, GW-scale: only very large players could take part (MNRE).
- PLI pays only on incremental sales over a base year, so a new or small firm with no base-year sales or below the thresholds gets nothing (scheme design, PIB 2026).
→Related schemes
Need help with PLI Solar PV?
Eligibility check, DPR and application file — ask us on WhatsApp.
Our interestHelp is our paid service. You can also apply for the scheme yourself.
¶Sources
- MNRE: Production Linked Incentive (PLI) — High Efficiency Solar PV Modules
- PIB, 20 Feb 2026: PLI with ₹1.91 lakh crore outlay, 836 applications, 14 sectors
- PIB Cabinet, 11 Nov 2020: PLI for 10 key sectors (outlay table)
Checked on 18 October 2026. For information only — confirm with the department or bank. Spotted a mistake? Report it.