01 Project at a glance

Total project cost
₹17.26 L
Term loan from bank
₹11.22 L
Promoter’s contribution
₹1.73 L
Subsidy
₹4.32 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-6.04 L
Average DSCR
-1.49
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Separate cream from bought milk, churn it to butter, boil it into ghee and sell 500 g packs; toned milk is a by-product.

Main product or serviceGhee Making Unit
Installed capacity per year (at 100%)10,000 units

04 Market

  • Households
  • Sweet shops and caterers
  • Ice-cream and confectionery makers
  • Kirana and grocery stores
  • Distributors and kirana shops
  • Direct sale to sweet makers and caterers
  • Own outlet or milk route

05 Plant and machinery

ItemQty₹Total ₹
Milk storage tank (× 2)170,00070,000
Balance tank115,00015,000
Milk homogeniser11,95,0001,95,000
Milk pasteuriser12,75,0002,75,000
Cream separator131,00031,000
Boiler11,65,0001,65,000
Pump118,00018,000
Chiller12,75,0002,75,000
Butter churning machine11,35,0001,35,000
Ghee boiling kettle185,00085,000
IBT-type chilling machine11,45,0001,45,000
Pouch filling machine12,15,0002,15,000
Other machinery and equipment (× 1 lot)120,00020,000
Total16,44,000

Pre-filled from: PMEGP sample project report — Ghee (prepared by Udyami/Samadhan); World Customs Organization – HS Nomenclature 2022 edition. Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Milk — 6,75,000 litres a year at ₹20 a litre at full capacity (report rate)
  • Packing material — ₹3.50 L a year lump sum

07 Cost of project

₹ in lakh
Plant and machinery16.44
Contingency0.82
Total fixed capital17.26
Working capital margin0.00
Total project cost17.26

08 Means of finance

₹ in lakh%
Promoter’s contribution1.7310.0
Subsidy4.3225.0
Term loan from bank11.2265.0
Total17.26100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance0.350.350.350.350.350.350.35
Insurance0.090.090.090.090.090.090.09
Total cost of operations3.313.313.313.313.313.313.31
Operating profit (EBITDA)-3.31-3.31-3.31-3.31-3.31-3.31-3.31
Depreciation2.592.201.871.591.351.150.98
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan1.211.050.860.670.480.290.10
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-7.12-6.56-6.04-5.57-5.15-4.75-4.39
Income tax0.000.000.000.000.000.000.00
Profit after tax-7.12-6.56-6.04-5.57-5.15-4.75-4.39

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-7.12-6.56-6.04-5.57-5.15-4.75-4.39
Depreciation2.592.201.871.591.351.150.98
Cash accruals (PAT + depreciation)-4.53-4.36-4.17-3.98-3.79-3.60-3.41
Term loan repaid0.861.731.731.731.731.731.73
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-5.39-6.09-5.90-5.71-5.52-5.33-5.14
Cash and bank-5.39-11.48-17.38-23.09-28.61-33.94-39.08

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)6.046.046.046.046.046.046.04
Reserves and surplus-7.12-13.68-19.72-25.30-30.44-35.20-39.59
Term loan outstanding10.368.636.905.183.451.730.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities9.280.99-6.78-14.08-20.95-27.43-33.55
Net fixed assets14.6712.4710.609.017.666.515.53
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-5.39-11.48-17.38-23.09-28.61-33.94-39.08
Total assets9.280.99-6.78-14.08-20.95-27.43-33.55

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-1.59-1.19-1.28-1.38-1.50-1.64-1.81
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-1.49
Lowest DSCR-1.81
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation2.592.201.871.591.351.150.98

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
111.221.210.8610.36
210.361.051.738.63
38.630.861.736.90
46.900.671.735.18
55.180.481.733.45
63.450.291.731.73
71.730.101.730.00

17 Licences and registrations

  • FSSAI licence (named in the report)
  • Udyam registration
  • GST registration
  • Trademark for the brand (optional, per report)
  • Boiler registration
  • State Pollution Control Board consent (dairy effluent)

18 Government schemes that may apply

  • Prime Minister's Employment Generation Programme (PMEGP)
  • PM Formalisation of Micro Food Processing Enterprises (PM FME)
  • Agriculture Infrastructure Fund (AIF)
  • Pradhan Mantri MUDRA Yojana (PMMY) – Shishu, Kishor, Tarun, Tarun Plus
  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)

19 Sources

  1. PMEGP sample project report — Ghee (prepared by Udyami/Samadhan) — https://pmegp.msme.gov.in/Home/DownloadDocument?fileName=Documents/ProjectSampleReport/Ghee_%28_Samadhan_Projects_%29.pdf
  2. World Customs Organization – HS Nomenclature 2022 edition — https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition/hs-nomenclature-2022-edition.aspx

This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.