Steel Re-Rolling Mill (MS Rounds, Angles, Channels, Tor Steel)

—

Prepared on: 13 November 2026 · Prepared with Building Business DPR (buildingbusiness.in)

01 Project at a glance

Total project cost
₹44.61 L
Term loan from bank
₹40.15 L
Promoter’s contribution
₹4.46 L
Sales · Year 3
₹0.00 L
Profit after tax · Year 3
₹-11.92 L
Average DSCR
-0.50
Break-even (% of capacity used)
—

02 Promoter and unit

Promoter name—
Business / firm name—
Legal formProprietorship
Address of the unit—
Applicant categoryGeneral · Rural

03 The project

Heat steel billets and scrap and roll them into rounds, flats, angles and twisted tor steel bars for building work.

Main product or serviceSteel Re-Rolling Mill (MS Rounds, Angles, Channels, Tor Steel)
Installed capacity per year (at 100%)10,000 units

04 Market

  • Building contractors and builders
  • Government construction works
  • Steel traders and hardware dealers
  • Fabricators
  • Sale through steel stockists
  • Direct supply to contractors

05 Plant and machinery

ItemQty₹Total ₹
230 mm rolling mill set: 7 mill stands, pinion stand, couplings, flywheel, reduction gear and one set of rolls131,22,00031,22,000
Coal-fired reheating furnace, 13 × 2.75 × 2 m17,10,0007,10,000
Cooling bed, 13 × 2 m11,17,0001,17,000
Shearing machine, 37 mm, 20 HP12,20,0002,20,000
Cropping machine, 12.5–25 mm, 10 HP180,00080,000
Twisting machines for tor steel (one up to 16 mm, two up to 25 mm) (× 3)100
Workshop machines: heavy lathe, shaper, pillar drill, grinder, welding set (× 1 lot)100
500 kVA step-down transformer with distribution and cables100
Total42,49,000

Pre-filled from: DC-MSME project profile — M.S. Rounds, Angles, Channels, Tor Steel etc.; World Customs Organization – HS Nomenclature 2022 edition. Prices in older reports will have gone up — enter today’s quotations.

06 Raw materials

  • Steel billets — 200 MT a month at ₹12,000 a MT in the profile
  • Re-rollable scrap — 120 MT a month at ₹10,000 a MT in the profile
  • Steam coal for the furnace — 30 MT a month in the profile
  • Refractories, lubricants and rolls

07 Cost of project

₹ in lakh
Plant and machinery42.49
Contingency2.12
Total fixed capital44.61
Working capital margin0.00
Total project cost44.61

08 Means of finance

₹ in lakh%
Promoter’s contribution4.4610.0
Term loan from bank40.1590.0
Total44.61100.0
Working capital loan (outside project cost)0.00

09 Key assumptions

Selling price₹0 per units
Raw material & packing cost₹0 per units
Capacity used each year60% · 70% · 80% · 80% · 80% · 80% · 80%
Term loan interest rate (% a year)11% · 84 months (Moratorium 6)
Working capital methodTurnover method (RBI) · Working capital interest (% a year) 11%
Income tax rate25%
Yearly price and cost rise0%

10 Production and sales

Year → (₹ in lakh)1234567
Capacity used60%70%80%80%80%80%80%
Production (units)6,0007,0008,0008,0008,0008,0008,000
Sales0.000.000.000.000.000.000.00

11 Projected profitability

Year → (₹ in lakh)1234567
Sales0.000.000.000.000.000.000.00
Raw material and packing0.000.000.000.000.000.000.00
Power and fuel0.000.000.000.000.000.000.00
Salaries and wages2.882.882.882.882.882.882.88
Rent0.000.000.000.000.000.000.00
Administration0.000.000.000.000.000.000.00
Selling and distribution0.000.000.000.000.000.000.00
Repairs and maintenance0.890.890.890.890.890.890.89
Insurance0.220.220.220.220.220.220.22
Total cost of operations4.004.004.004.004.004.004.00
Operating profit (EBITDA)-4.00-4.00-4.00-4.00-4.00-4.00-4.00
Depreciation6.695.694.844.113.492.972.52
Preliminary expenses written off0.000.000.000.000.000.000.00
Interest on term loan4.353.773.092.411.731.050.37
Interest on working capital0.000.000.000.000.000.000.00
Profit before tax-15.03-13.45-11.92-10.51-9.22-8.01-6.89
Income tax0.000.000.000.000.000.000.00
Profit after tax-15.03-13.45-11.92-10.51-9.22-8.01-6.89

12 Cash flow

Year → (₹ in lakh)1234567
Profit after tax-15.03-13.45-11.92-10.51-9.22-8.01-6.89
Depreciation6.695.694.844.113.492.972.52
Cash accruals (PAT + depreciation)-8.34-7.76-7.08-6.40-5.72-5.04-4.36
Term loan repaid3.096.186.186.186.186.186.18
Owner’s drawings0.000.000.000.000.000.000.00
Surplus after repayment-11.43-13.94-13.26-12.58-11.90-11.22-10.54
Cash and bank-11.43-25.37-38.63-51.21-63.11-74.33-84.87

13 Projected balance sheet

Year → (₹ in lakh)1234567
Capital (own + subsidy)4.464.464.464.464.464.464.46
Reserves and surplus-15.03-28.48-40.40-50.91-60.13-68.14-75.03
Term loan outstanding37.0630.8924.7118.5312.356.180.00
Working capital loan0.000.000.000.000.000.000.00
Total liabilities26.496.87-11.23-27.92-43.31-57.50-70.57
Net fixed assets37.9232.2327.4023.2919.8016.8314.30
Preliminary expenses not written off0.000.000.000.000.000.000.00
Current assets (stock and debtors)0.000.000.000.000.000.000.00
Cash and bank-11.43-25.37-38.63-51.21-63.11-74.33-84.87
Total assets26.496.87-11.23-27.92-43.31-57.50-70.57

14 Ratios and break-even

Year1234567
Debt service coverage ratio (DSCR)-0.54-0.40-0.43-0.47-0.51-0.55-0.61
Break-even (% of capacity used)———————
Cash break-even———————
Average DSCR-0.50
Lowest DSCR-0.61
Payback period—

15 Depreciation

Year → (₹ in lakh)1234567
Depreciation6.695.694.844.113.492.972.52

Written-down value method at Income-tax Rules block rates (building 10%, plant & machinery 15%, furniture 10%, computers 40%). Change them if your CA uses other rates.

16 Term loan repayment

YearOpeningInterestTerm loan repaidClosing
140.154.353.0937.06
237.063.776.1830.89
330.893.096.1824.71
424.712.416.1818.53
518.531.736.1812.35
612.351.056.186.18
76.180.376.180.00

17 Licences and registrations

  • Udyam registration
  • GST
  • State Pollution Control Board consent to establish and operate
  • Factory licence under the Factories Act
  • BIS certification under the steel Quality Control Order (for example IS 1786 bars, IS 2062 structural sections)
  • High-tension power connection approval

18 Government schemes that may apply

  • Credit Guarantee Fund Trust for Micro and Small Enterprises (CGTMSE)
  • Stand-Up India

19 Sources

  1. DC-MSME project profile — M.S. Rounds, Angles, Channels, Tor Steel etc. — https://www.dcmsme.gov.in/publications/pmryprof/meatllurgical/ch15.pdf
  2. World Customs Organization – HS Nomenclature 2022 edition — https://www.wcoomd.org/en/topics/nomenclature/instrument-and-tools/hs-nomenclature-2022-edition/hs-nomenclature-2022-edition.aspx

This report is a projection from the figures entered by the promoter. It is not a bank appraisal or a guarantee of a loan or subsidy. Check every figure with current quotations and your chartered accountant before submitting it.